Project Plan
Write Functional Specification0%0%6 days3 days3 days
Mon 3/6/06
Mon 3/13/06 Stoltmann Kerry[50%]User Signoff on Specification0%0%5 days0 days0 days
Tue 3/14/06
Mon 3/20/06 Programming and Unit Testing0%0%6.67 days5 days5 days
Tue 3/21/06
Wed 3/29/06 Wallin Adam Team[75%]Coordinator Testing0%0%8 days4 days4 days
Mon 4/10/06
Wed 4/19/06 Stoltmann Kerry[50%]
(wow, a whole month for SDLC, must be RAD)
Mon 3/6/06
Mon 3/13/06 Stoltmann Kerry[50%]User Signoff on Specification0%0%5 days0 days0 days
Tue 3/14/06
Mon 3/20/06 Programming and Unit Testing0%0%6.67 days5 days5 days
Tue 3/21/06
Wed 3/29/06 Wallin Adam Team[75%]Coordinator Testing0%0%8 days4 days4 days
Mon 4/10/06
Wed 4/19/06 Stoltmann Kerry[50%]
(wow, a whole month for SDLC, must be RAD)